By Our Correspondent
PURI/BHUBANESWAR: Today, on the third day of chariot construction, the chariot builders arrived at the chariot yard before 8:00 AM and started the chariot construction process.)
Today, out of the 42 tumbas required for the three chariots, 21 tumbas have been measured and rolled by the Karati Sevaks, providing them with 7 tumbas for the three chariots.
From the above-mentioned tomb forts, the servants of the three chariots of Maharana have completed the work of destroying and encircling ten tomb forts in Barishi till today.
Today, out of the total 7 tombs provided to the Taladhwaj Rath Chali, the construction workers have completed the work of 4 tombs and are continuing the work of 3 more tombs.
Similarly, even today, out of the seven fortified tombs that have been added to the chariot of the Goddess, the Devi Rath Maharana Sevaks have completed the work of carving three tombs and are continuing the work of carving the other four tombs.
Similarly, as of today, out of the 7 tombs provided to the Nandighosha Rath Chali, the work of 3 tombs has been completed, and the work of 4 more tombs is in progress.
*Temporary blacksmith’s shop*
After the Shaal Puja and temporary blacksmiths prepared the shaals for the construction of the chariots in the Dola Vedy area yesterday, the construction of the auspicious arkanta began with auspicious arkantas. Today, the Ojha Sevaks of the three chariots continued the work of cutting 10 mm size iron rods to build the arkantas and started the construction of the arkantas.
*Total Builder Attendance*
*Tiniratha Maharana Sevak – 25
*Three Chariots Karti Sevak – 4
*Servant of the Three Chariots – 6
*Tiniratha Bhoi Sevak – 14
*Rathakhala Assistant (Panibala) 1
Total – 50 people