By Our Correspondent
PURI:Today, on the 25th day of the chariot construction, the workers who built the three chariots arrived at the Rathkhala before 8:00 a.m., gave their presentations, and proceeded with the construction work as advised by the Chief Maharana.
By yesterday, the construction of 32 wheels of the three chariots had been completed and the construction of the 14 chariots had begun)
Today, the construction of 33 wheels of the trirathas has been completed, and the measuring marks for the girders of the girders have been completed before the girders are laid.
Three-Rat Four-Nahaka Chaupat work in final stage / Three-Rat Two-Way Dekha Chaupat work started.
Out of the 42 wheels of the three chariots, the construction of 33 wheels of the three chariots has been completed till today. After the construction of 9 more wheels of the three chariots, the total construction of 42 wheels of the three chariots will be completed.
Out of the 14 wheels of the Taladhwaj Rath, 9 wheels have been completed and the construction of the remaining five wheels is in progress. Today, the Maharana Sevaks of the Taladhwaj Rath have completed the decoration of the 10th and 11th wheels, the tumba and singda, and have finished putting the measurement marks on the 12th and 13th wheels for the tumba and singda. In addition, the 12th and 13th wheels have been completed, the tumba and singda have been cut and the mouth has been completed.
The construction of 10 wheels of the Darpa Dalan Rath has been completed, the 11th wheel’s tumba’s pai uguba is completed and the pai kalsha is in progress. Along with this, the finishing touches for the Muhanta, Niradi and Bhuin Chauta of the Prabhakar Dalan Rath have been completed. In addition, the Maharana Sevaks of the Prabhakar Dalan Rath have completed the work of four four-nahaka and three-nahaka chaupats and are continuing the work of carving eight corner parts in them.
Out of the 16 wheels of the Nandighosha Rath, 14 wheels have been completed till today. The 15th wheel has been completed and the tumba singada has been cut and the face has been finished. In addition, the frame of the Nandighosha Rath has been completed, 12 ground frames have been marked for the frame, and the work of cutting eight corners of the four Nahakas and two Nahakas has been completed, and the work of cutting the remaining two Nahakas has reached the final stage.
In addition, all the wheels of the three chariots in the outer chariot shed have been shifted to the new shed today. This step has been taken to provide protection to the chariot wheels from the heat of the storm. Earlier this evening, the three chariots’ servants rolled 27 wheels under police protection and kept them safely in the new shed.
The three chariots are carved with a lion-like shape in the corner or corner of the carve, and the finished shapes are polished and ornamented with ornaments.
At the temporary blacksmith shop in Dolavedi, the blacksmiths of Ojha have continued to make the three chariots’ clock faces, the bells, the bells, and the bells of the foot.
The presence of the charioteer*
*Tiniratha’s Maharana Sevak – 77
*Tiniratha’s servant – 76
*Three Chariots Karti Sevak – 4
*Servant of the Three Chariots Ojha Kamar – 20
*The servant of the Three Chariots – 21
*Tum Bindha Craftsman – 2
*Rathakala Assistant (Water Bottle) – 1
Total – 201 people