By Our Correspondent
PURI:Today, on the twelfth day of chariot construction, the workers who built the three chariots arrived at the chariot yard at 8:00 AM and began the construction work after receiving the guidance of the chief Maharana.
Today, the three chariots are adorned with ornaments, bracelets, and auspicious attire.
The three-wheeled Pai Bakla Anukul has been completed today before Pai Bindha.
The measurement mark on the foot for the foot piercing is finished.
Chaka Dera Nithi will be held on Bhanuri Tithi, with this aim in mind, the chariots are being prepared, the preliminary preparations are underway, the three-time chief Maharana’s Marg Darshan
Yesterday, the work of building a Singada in each Nahaka Tumba was completed by the Bhoi Sevaks of the three chariots. In addition, the Maharana brothers completed the work of building 11 water tanks, 9 water tanks, and 12 water tanks for the three chariots…)
Today, the three Rathas Maharana Sevaks have completed the preliminary preparation work for the preparation of the Nahaka Chak.
This afternoon, after the cutting of the three Rathas through the Rath Amin Bhoi Sevak, the “Paibakla” Anukul Puja was performed by the Chief Maharana of the three Rathas, after which the fellow Maharana Sevaks placed the feet on the connecting tumb or Singda and the Chief Maharana marked the measurement mark, after which the fellow Maharana Sevaks cut the remaining feet and completed the face-saling work. In addition, today, the cutting of the feet of the Nahaka Chak Singda and the face-saling work were completed in two parts.
In addition, the work of 4 12-foot-wide arches of three chariots has been completed, and the work of tying two arches on both sides has been completed. In addition, out of 12 kudikas (for fastening the five rods) of three chariots, the work of 9 kudukas has been completed, and in the remaining tumbas, the tumbas have been dug out and the tumbas have been placed in the middle of the tumbas for the singada wall.
The servants of the Three Chariots have carved the image of a lion and a lioness on the gujjar.
At the temporary blacksmith shop in Dolavedi, the three-wheeled blacksmiths have completed the decoration and bracelets of the Nahaka tombs and have provided them with three chariots. After preparing the decoration and bracelets for the remaining tombs, they have continued to make the ar kantar.
The Deputy Chief Administrator and District Magistrate is supervising the daily construction work of the chariots. This evening, he visited the chariot yard to learn about the progress of the chariot construction and discussed the construction progress with the head of the three chariot workshops, Maharana, and Bhoi Sevak. The Deputy Chief Administrator expressed satisfaction with the construction work and requested the Shrimandir for more lighting in the chariot workshop.
The Deputy Chief Administrator has instructed the Assistant Engineer of the Electricity Department.
The presence of the chariot builder*
*Tiniratha Maharana Sevak -78
*Three Chariots Karti Sevak – 4
*Servant of the Three Chariots – 15
*Servant in the form of a three-wheeled chariot – 21
*Tiniratha’s servant -62
*Tumbi Bindha Craftsman – 2
*Rath Khola Assistant (Water Bucket) 1
Total – 183 people